ODA publishes Annual Report after a year of strong progress

Olympic Delivery Authority

21 July 2008

The Olympic Delivery Authority (ODA) today published its Annual Report and Accounts for 2007 – 2008, following a year when the ODA has delivered virtually all, and exceeded some, of its ‘Dig, Demolish, Design: Milestones to Beijing’.

Publishing the report, Chairman John Armitt said: 'Thanks to the hard work of the team, impressive progress has been made over the last year with the Olympic Park transformed and construction already underway ahead of schedule. This has been reflected by the International Olympic Committee (IOC) who praised the progress and gave us a 9.75 out of 10.

'We have created strong foundations and we are firmly on track to deliver but there is no room for complacency. This is a unique project with an immoveable deadline. It is one of the biggest business challenges in the world and one of the biggest projects in the construction industry.

'75p of every pound we spend is for long-term regeneration so a great deal of work is already being done to create a lasting legacy.'

Olympics Minister, Tessa Jowell said: 'We are now very well set for the next crucial big build stage that has already begun in earnest with construction starting early on the Stadium and the Aquatics Centre.

'I am confident that with the world class team we have in place at the ODA, we will continue to make good progress and deliver a fantastic games for London and the whole UK.

'No one is complacent, but to have got so far on budget and on time is cause for congratulations to the whole team.'

The milestones hit by the ODA in the past year include:

  • 192 buildings demolished
  • over one million cubic metres of soil excavated to shape the park
  • two six kilometre tunnels and 200km of cabling complete
  • contractors appointed to build the ‘Big Four’ Olympic Park venues and design work well-advanced
  • construction started on the Olympic Stadium three months ahead of schedule
  • construction started two months early on Aquatics Centre
  • construction started on the Olympic Village.
‘Dig, demolish, design: milestones to Beijing’ have been achieved in virtually every regard. The ODA has set out its next set of milestones for the year ahead, ‘The Big Build: Foundations’ is available for download.

– Ends –

For further information please contact the Olympic Delivery Authority Press Office on +44 (0)203 2012 700.

Find out the latest from London 2012 HQ on our blog.

Related publications

  • ODA Annual Report and Accounts 2007-2008
    The ODA's Annual Report and Accounts 2007-2008 (PDF, 5MB)

Related content

News

Blog