London 2012 today finished the year on track as the Olympic Delivery Authority (ODA) announced the completion of demolition on the sites of the ‘Big 5’ venues – the Olympic Stadium, the Aquatics Centre, the IBC/MPC, the VeloPark and the Olympic Village – and they, together with the London 2012 Organising Committee (LOCOG) gave an update on the progress made during 2007.
Key achievements over the last year include:
- Lloyds TSB announced as first Tier One Partner.
- New London 2012 brand unveiled.
- Announcement of ODA lifetime budget.
- London 2012 Roadshow tours UK.
- Completion of powerlines tunneling on time and to budget.
- Vision for Cultural Olympiad announced.
- Strong endorsement from IOC Co-ordination Commission on progress to date.
- Velodrome design competition winner announced.
- EDF Energy announced as second Tier One Partner and first Sustainability Partner.
- Olympic Park handed to the ODA on time by the London Development Agency (LDA).
- Planning permission for the Park secured.
- Planning permission secured for enhanced sailing facilities at Weymouth & Portland.
- Adidas announced as third Tier One Partner.
- London 2012 Transport Plan published.
- London 2012 Sustainability Plan launched.
- Innovative Stadium designs revealed.
- Deloitte announced as Tier Two Professional Services supporter.
- Demolition complete on all five main venue sites.
In 2008, London 2012 will: - Receive the Olympic and Paralympic Flags in Beijing as London’s Olympiad begins.
- Launch pre-Games training camp guide.
- Intensify work to clean the site of decades of contamination.
- Announce more Tier One and Tier Two sponsors.
- Award construction contracts for Velodrome and Aquatics Centre and developer for IBC/MPC.
- Begin the construction phase in earnest with number of workers increasing dramatically.
- Launch the Cultural Olympiad.
- Over 90 per cent of demolition materials being recycled or reused.
- Over two-thirds of buildings demolished.
- 93 per cent of site investigated.
- 49 per cent of site cleared
- Both 6km tunnels running underneath the Olympic Park completed.
- More than a third of the 200km cabling in the tunnels installed.
- Temporary diversion of powerlines around Olympic Village site completed.
- Vacant possession gained, giving London 2012 access to the vast majority of the
Site. - Three of five temporary bridges to aid logistics in place.
- First temporary road being constructed.
- Preferred bidder appointed for Olympic Park Energy Centre and networks.
- Planning permission granted for wind turbine at Eton Manor.
- Planning application submitted for primary substation.
- 450m of new river wall installed on the Aquatic Centre, widening river by eight
metres. - Widening of channels at Prescott Lock completed.
- High Speed 1 rail link in operation between St. Pancras International and mainland Europe.
- First additional DLR car delivered and two new DLR platforms built at Stratford Regional Station.
- Two tunnels for DLR extension under River Thames completed in July 2007, ahead of schedule.
- Designs for Olympic Stadium revealed.
- 100 per cent of buildings on Stadium site demolished.
- Work expected to start on site of Stadium ahead of schedule.
- Demolition completed on Olympic Village site.
- Temporary diversion of powerlines completed, to enable early construction to begin.
- Architectural Panel appointed for design of Village.
- Demolition completed on sites of the ‘Big 4’ venues: Aquatics Centre, VeloPark,
Olympic Stadium and the IBC/MPC. - 450m of river walls created on site of Aquatics Centre, widening the river by eight metres.
- Designs published for the Olympic Stadium, VeloPark and the Aquatics Centre.
- ODA, London Development Agency, local boroughs, Mayor of London and
central government working in partnership. - Plans moving forward to agree the vision for regeneration after the Games.
– Ends –