More than 100 columns have been built to support the Olympic Stadium's west and south standsThe foundations for the Stadium are also nearing completion, with more than 3,500 of the 4,000 permanent piles installed in the ground.
On the south of the Stadium site 200 concrete supports are being cast. These will support the 25,000 permanent seats in the lower level of the Stadium.
Work is also underway on the supports for one of the five bridges that span the waterways around the Stadium island site. During the Games this bridge will be one of the main ways for spectators to reach the Stadium.